NYCT Indefinite Quantity for Construction Inspection


 


HAKS provided construction inspection services in the fields of mechanical, electrical, civil and structural engineering under an on-call contract with New York City Transit. HAKS performed project inspection, ensuring that work was completed according to contract specifications and NYCT requirements. We were also responsible for constructability review, construction phasing review, cost estimating, scheduling, safety inspections and value engineering. Projects included:                             

  • Rehabilitation of Nassau Street/Fulton Street Stations (J, M and Z lines)
  • Rehabilitation of Lexington Avenue/59th Street Stations (4, 5 and 6, N and R lines)
  • Rehabilitation of Queensboro Plaza Station (7 and N lines)
  • Rehabilitation of Main Street Station and RTO Facilities (7 line)
  • Rehabilitation of Queens Plaza Station (E, F, G, and R lines) (design phase)
  • Rehabilitation of Roosevelt Avenue/74th Street Station (E, F, G and R lines) (design phase)
  • 103rd, 110th, 116th and 125th Street Stations (1 and 9 lines)
  • 174th Street, West Farms/South E. Tremont Avenue, Bronx Park east, Pelham Parkway, Allerton Avenue, Burke Avenue, and Gunhill Road Stations (2 and 5 lines)
  • Myrtle/Wyckoff Avenue Station (L and M lines)
  • Penn Station (A, C & E lines)
  • Coney Island/Stillwell Avenue Station (F, Q, and W lines)
  • Lead-based paint project sites at City Hall Station, No. 7 Station rehabilitation, Gates/Lorimer/Chauncy, and Times Square Complex
  • 240th Street Maintenance Shop
  • Subway station rehabilitation at Kings Highway, 86th Street, Ditmars Boulevard, and Coney Island-Stillwell Avenue (N line)
  • Modernization at 34th Street and 8th Avenue Subway Station
  • Atlantic Avenue interlocking reconfiguration
  • Installation of CCTV systems at 98 platforms
  • Security work including installation of public address systems for emergency situations; conduit and cable runs for CCTV (1 line from Van Cortland Park to Dyckman Street)
  • Installation of new fire detection and alarm system, including sprinkler systems at six locations
  • Installation of circuit breakers, signal equipment enclosure, access platform and other facilities for the Far Rockaway Test Track Area
  • Furnishing and installing a power rectifier at the Lexington Avenue/East 57th Street Substation
  • Structural rehabilitation of the Culver Line Viaduct
  • Structural rehabilitation, painting, tunnel lighting and firefighting water line for the Flushing Line, IRT Division
  • Furnishing and Installing power rectifier equipment for Nostrand Avenue Substation
  • Structural rehabilitation of viaduct crossing Jamaica Bay (A line)
  • Structural rehabilitation of elevated line, surface preparation and painting of Flushing line from Queensboro Plaza to Hunters Point Station